制約による配置の違い
Name
Start
End
Effort
Resources
Responsible
Jul 2026
Aug 2026
Sep 2026
Oct 2026
27
03
10
17
24
31
07
14
21
28
05
Icon ① ASAP: できるだけ早く
ID: asap
2026-08-03
2026-08-07
5.0
Alice (alice)
Icon ④ 期限を検査するタスク
ID: checked
2026-08-03
2026-08-14
10.0
Carol (carol)
Icon ⑤a 優先度 900
ID: high
2026-08-03
2026-08-07
5.0
Bob (bob)
Icon ⑤b 優先度 100
ID: low
2026-08-10
2026-08-14
5.0
Bob (bob)
Icon ⑥ フラグと責任者
ID: tagged
2026-08-10
2026-08-12
3.0
Alice (alice)
Alice
Icon ③ 開始日を固定
ID: fixed
2026-08-17
2026-08-21
5.0
Alice (alice)
Icon ② ALAP: できるだけ遅く
ID: alap
2026-09-23
2026-09-29
5.0
Bob (bob)
Icon 納品期限
ID: deadline
2026-09-30
2026-09-30
0.0
Container Task
Normal Task
Milestone
Off-duty period